Design an Apron Floodlighting layout to comply with MOS 139 for Code 4D Aircraft
Procure and Install floodlighting poles and LED fittings.
Modify existing AGL Control System.
Setup and Commission.
Carried out 12 monthly Technical Inspection of the AGL equipment as per CASR 139.235-1. & CASR 139.240-2(b)
Provided condition assessment report of all AGL equipment.
Reviewed compliance of AGL equipment and provided written statement for inclusion in the Aerodrome Manual.
Reviewed the Aerodrome Manual and offered suggested improvements.
Made recommendations to improve reliability of AGL system and rectify any Non-compliances.
Provided budgetary pricing for future upgrades
2017 August Audit and Condition assessment of Airfield Ground Lighting
Carried out 12 monthly Technical Inspection of the AGL equipment as per CASR 139.235-1. & CASR 139.240-2(b)
Provided condition assessment report of all AGL equipment.
Reviewed compliance of AGL equipment and provided written statement for inclusion in the Aerodrome Manual.
Reviewed the Aerodrome Manual and offered suggested improvements.
Made recommendations to improve reliability of AGL system and rectify any Non-compliances.
Provided budgetary pricing for future upgrades