Murputja

September 2014  Murputja Aerodrome - Installation of new Solar Lights 

Remove all old Avlites.

Clean ground surface around light foundations 

Mount new AV70 Avlites to prevent water ingress.

Replace windsock 

Test and Commission newly installed lighting.

July 2011 Murputja Aerodrome - Maintenance Inspection of Installed AGL.

Review installed AGL equipment replace Avlites effected by water ingress or damaged by traffic.

Make repairs where possible.

Service IWDI and replace Wind Sock

Make recommendations for future improvements.

April 2012  Murputja Aerodrome - Maintenance Inspection of Installed AGL.

Review installed AGL equipment replace Avlites effected by water ingress or damaged by traffic.

Undertake routine maintenance, wash fittings, remove weeds etc, make repairs where possible.

Service IWDI and replace Wind Sock

Make recommendations for future improvements.

 

Back to projects