September 2004 RAAF Base Amberley - Audit and Condition assessment of Airfield Ground Lighting
Carried out 12 monthly Technical Inspection of the AGL equipment as per CASR 139.235-1. & CASR 139.240-2(b)
Provided condition assessment report of all AGL equipment.
Reviewed compliance of AGL equipment and provided written statement for inclusion in the Aerodrome Manual.
Reviewed the Aerodrome Manual and offered suggested improvements.
Made recommendations to improve reliability of AGL system and rectify any Non-compliances.
Provided budgetary pricing for future upgrades
This report was used to achieve funding for the complete replacement of the AGL system
July 2003 RAAF Base Amberly - Installation of apron edge lighting,